The construction started in October 2024 and the personnel were evacuated on November 16, 2025, lasting 3 months. The project was led by CIMC and jointly cooperated with JIMAN to carry out the marine juice project. Our company was responsible for the entire marine juice module prefabrication and installation, the prefabrication and installation of all clean pipes, pressure pipes, and stainless steel pipe rack supports, and in addition, all the work for the pipes, valves, and equipment that required insulation. All the fresh-squeezed juice pipes, vacuum pipes, CIP pipes, tap water, hot water, pipes, etc. below DN100 in this project used automatic welding, 100% endoscopy, and the preparation of inspection documents, etc., achieve the first unsterile pipeline in China, and received high praise from the shipowner, juice company, CIMC JIMAN, and other domestic and foreign parties